Last tracks laid in Line 13 extension, trial operation to begin this year 2018-05-31
Track construction on the second and third phases of Metro Line 13 were completed on Wednesday and its trial operation will commence before the end of the year, local Metro operator announced.
In order to finish construction on time, more than 1,100 workers and 100 machines took part in the project, said Shanghai Shentong Metro Group.
A more advanced track-laying machine was used for the first time on China's mainland, increasing efficiency and safety. While traditional track layers can finish laying 33.9 meters of track a day, the new machine can achieve 50 meters.
In order to finish construction on time, more than 1,100 workers and 100 machines took part in the project, said Shanghai Shentong Metro Group.
A more advanced track-laying machine was used for the first time on China's mainland, increasing efficiency and safety. While traditional track layers can finish laying 33.9 meters of track a day, the new machine can achieve 50 meters.
Application Status
04-16 | 21315227 | Processing |
03-12 | 21315226 | Processing |
09-26 | 21315225 | Processing |
Inquiry Status
02-29 | 02131558 | Received |
03-06 | 02131557 | Received |
11-14 | 02131556 | Received |
FAQ
Q: Q: Is there a place where I can get...
A: A: Log on to http://touch.shio.gov....
A: A: Log on to http://touch.shio.gov....
Q: Q: What is the easiest way to set u...
A: A: 1. Log on to http://touch.shio.g...
A: A: 1. Log on to http://touch.shio.g...
Q: Where can I get an English map of S...
A: English maps of Shanghai are availa...
A: English maps of Shanghai are availa...